How long does an extension take? From survey to sign-off

Roofer fixing new roof tiles on a house under construction

Short answer: allow four to six months from the first survey to a finished single-storey extension. The build itself is often 10 to 18 weeks; design, approvals and party wall notices take the rest. Planning permission adds about eight weeks.

A typical timeline

StageTypical timeWhat happens
Survey visit and quote1 to 3 weeksWe see the job, measure up and send an itemised price
Design and structural calculations3 to 6 weeksDrawings, steel sizes and a specification
Planning permission (if needed)About 8 weeksCouncils aim to decide householder applications within eight weeks
Building Regulations5 weeks to 2 months for full plansPlans are checked before work starts
Party wall notices1 to 2 months’ noticeOften served while the design is checked
The build10 to 18 weeksGroundworks to decoration, depending on size
Sign-off1 to 2 weeksSnagging, the completion certificate and your paperwork

Several stages run side by side: the party wall notices and Building Regulations checks often run during the planning decision.

Week by week on site

  • Weeks 1 to 3: set-up, demolition, digging and pouring foundations, drainage. Building control inspects the foundations.
  • Weeks 3 to 7: walls up to roof level, steels in, roof structure on.
  • Weeks 7 to 10: roof covering, windows and doors in: the extension is weathertight.
  • Weeks 10 to 14: first fix electrics and plumbing, insulation, plastering, then knocking through.
  • Weeks 14 to 18: flooring, kitchen, second fix, decoration and snagging.

What causes delays

  • Long lead times for steel, glazing, roof lanterns and kitchens. Order early.
  • Changes to the design once the work has started.
  • Unknowns in the ground: old drains, tree roots or soft clay.
  • Wet weather during groundworks and roofing.
  • Waiting for building control inspections or a party wall award.

Questions people ask

Can we stay at home during the build?

Usually, yes. The new space is built outside first, and the knock-through happens near the end. Expect a few days without a kitchen; we’ll plan a temporary one with you.

When is the best time of year to build?

Starting groundworks in spring or early summer avoids the wettest months, but good builders work all year. It’s more important to have approvals and materials ready.

What paperwork should I get at the end?

The Building Regulations completion certificate, electrical and gas safety certificates, the FENSA or CERTASS certificate for windows, and any guarantees. Keep them for when you sell.

Planning an extension for next year? Book a survey visit or call 07802 758763.

Last checked: 27 November 2026. Rules and figures change; check the linked sources before you rely on them.

Book a survey visit

Tell us about your project

Choose a day that suits you for a survey visit and send a few photos if you have them. We’ll confirm a time and talk the job through.

Phone: 07802 758763

Email: hello@bloom-building.co.uk

Monday to Friday, 8am to 5pm

We use these details only to reply to your enquiry. Privacy policy