Short answer: if your extension or loft conversion works on a shared wall, builds on the boundary or digs foundations close to next door, you must serve notice under the Party Wall etc. Act 1996, usually one or two months before work starts. The Act applies in England and Wales whether or not you need planning permission.
Which works need a notice
| Work | Notice | Minimum warning |
|---|---|---|
| Work on a shared (party) wall: cutting in steels, raising it, removing chimney breasts | Party structure notice | Two months |
| Building a new wall on or astride the boundary | Line of junction notice | One month |
| Digging foundations within 3m of a neighbour’s building and deeper than their foundations (or within 6m in some cases) | Notice of adjacent excavation | One month |
Loft conversions on terraced and semi-detached houses nearly always need a party structure notice, because the new steels sit in the party wall. Rear extensions often need an excavation notice.
What happens after you serve notice
- Your neighbour has 14 days to reply. They can consent, or dissent and appoint a surveyor.
- If they don’t reply within 14 days, a dispute is assumed and surveyors are appointed.
- The surveyor, or two surveyors, prepare a party wall award setting out how the work is done, a record of the neighbour’s property before it starts, and access arrangements.
- The person doing the work normally pays the reasonable surveyors’ fees.
- A notice lapses if the work hasn’t started within a year.
How to make it easy
- Talk to your neighbours before the notice lands. A letter from a stranger reads very differently from one you have explained over the fence.
- Share the drawings and the expected dates.
- Take dated photos of shared walls and boundaries before work starts.
- Agree a single surveyor if your neighbour is happy to; it costs less than two.
The government’s Party Wall etc. Act guidance includes example notices.
Questions people ask
Is a party wall agreement the same as planning permission?
No. Planning permission and Building Regulations are separate. You can have planning permission and still need to serve party wall notices.
Can my neighbour stop the work?
No, the Act doesn’t give a veto. It makes sure the work is done properly and that any damage is put right.
Who serves the notice?
The building owner, which is you. Many people ask a party wall surveyor to prepare and serve it. We tell you at the survey visit which notices your job is likely to need.
Planning an extension or loft on a terraced or semi-detached house? Book a survey visit or call 07802 758763.
Last checked: 27 November 2026. Rules and figures change; check the linked sources before you rely on them.
